Getting Close To Lock-Up Stage
Greetings followers of Funding The Dream!
I know it's been a while, but I decided to hold off taking pictures of the outside by about a week because we were so close to completing the brick work and having the scaffold come down, which you can now see is complete. They just put the trusses' for the garage up and we suspect that the roof cover for the garage, theater room and alfresco will happen Monday of the coming week. We are hopeful the bricks will be cleaned shortly after that as well as work inside commencing this week too. We have a site walk-through on Tuesday at 2:00 with our site supervisor to point out a few odds and ends that may need some attention, but beyond that we're pretty pleased with both the progress and the quality of work. We'll have a better read on the scheduling of trades and perhaps a date or month that handover might occur, once we have this meeting, so stay tuned!